BRE365 testing for planning
Soakaway tests for planning: what Surrey and Hampshire councils ask for
If your application or a planning condition involves a soakaway, the drainage reviewer wants measured evidence that the ground will take the water. This guide sets out what the two county flood authorities and five local councils around Farnham publish about that evidence.
We carry out BRE365 percolation testing from Farnham across Surrey and Hampshire. A BRE365 percolation test is £1,500 fixed for one test location. That covers excavation of the trial pit, water, the three fills with Percologger monitoring, reinstatement and your report. There is no VAT to add. Further test locations are quoted separately.
Sources checked on 19 November 2026. Council documents change, and some of the local ones are several years old. Every point below links to the document it comes from, so you or your designer can confirm the current wording.
Who decides whether a soakaway is acceptable?
Your borough or district council decides the planning application. On major development it consults the county council as Lead Local Flood Authority. Surrey County Council is the flood authority for Waverley and Guildford. Hampshire County Council is the flood authority for Rushmoor, Hart and East Hampshire.
Major development usually means ten or more homes, or a site of a hectare or more. On smaller schemes the county is not a statutory consultee, so the local council and Building Control set the requirement. Surrey still publishes separate guidance for non-major development, which it defines as one to nine dwellings or sites under a hectare.
Both counties follow the same order of preference for rainwater. Infiltration into the ground comes before a watercourse or a sewer, which is why the infiltration test is asked for so often.
The rules most reviewers apply
These points come up in the national and county documents. Your designer applies them; the test supplies the measured figure they depend on.
| Point | What is asked for | Where it is written |
|---|---|---|
| Test method | Infiltration testing in accordance with BRE Digest 365. | Surrey standard condition; Hampshire technical note |
| Repeat fills | The test repeated at least three times, with the lowest rate at each location used for design. | Hampshire technical note; Hampshire planning guidance |
| Position and depth | As close as possible to the proposed soakaway and at a similar depth. | Hampshire technical note |
| Groundwater | At least one metre of unsaturated ground between the base of the soakaway and the highest groundwater level. | National standards for SuDS; both counties |
| Minimum rate | Infiltration treated as viable above 1 x 10-6 metres per second. | Hampshire technical note; national standards |
| Emptying time | The designed soakaway half-empties within 24 hours. | National standards for SuDS |
| Distance from buildings | Not within five metres of a building or road. | Approved Document H, paragraph 3.25 |
The half-emptying check and the distance from buildings belong to the soakaway design, not the trial pit. The test result is one input to them.
Surrey: Waverley and Guildford
Surrey County Council’s design guidance for major development includes the standard condition it asks councils to attach. The first item the condition requires is the results of infiltration testing completed in accordance with BRE Digest 365, with confirmation of groundwater levels. Where infiltration is proposed it also asks for confirmation of a one metre unsaturated zone below the soakaway and of half-drain times.
If test results are not available when you apply, Surrey asks for a justification and a suitable desk study of ground conditions. It gives a working brownfield site where trial pits cannot be dug as an example. Its guidance on discharging the conditions expects final information at that stage, not assumed or preliminary figures.
For smaller schemes, Surrey’s non-major guidance says infiltration test results should accompany planning applications, and asks the applicant to confirm the site infiltration rate and the one metre separation from the highest recorded groundwater.
Waverley Borough Council (Farnham, Godalming, Haslemere, Cranleigh)
Policy CC4 of Local Plan Part 1 requires sustainable drainage on major developments and encourages it on smaller schemes, with no increase in the volume or rate of runoff. The council’s validation checklist (version 12) asks for a surface water drainage strategy for all scales of development where surface water will be created or affected.
Waverley’s 2015 flood risk assessment describes the north and west of the borough, including Farnham, Godalming and Haslemere, as highly compatible with infiltration drainage, and the south and east as having very significant constraints. That is a borough-wide map. It does not replace a test on your plot.
Guildford Borough Council
Policy P11 of Guildford’s Development Management Policies (adopted March 2023) covers sustainable surface water management. It requires at least one metre of vertical distance between an infiltration feature and the maximum likely groundwater level, and compliance with the county’s guidance.
The council’s drainage requirements page sets extra requirements for major projects. Its surface water advice note expects soakaways to be shown to work through an assessment under BRE Digest 365, with a back-up attenuation scheme where on-site infiltration is proposed. The note dates from 2015, so check it against the county’s current guidance.
Hampshire: Rushmoor, Hart and East Hampshire
Hampshire County Council publishes the most detailed test requirements of the two counties, in its infiltration testing and groundwater monitoring technical note. The main points are:
- Testing follows the BRE Digest 365 (2016) method and is repeated at least three times.
- The test is carried out as close to the proposed soakaway as possible, at a similar depth.
- The worst-case rate is used for design unless the county agrees otherwise. An average is listed as a common mistake.
- An incomplete test must not be extrapolated. The note expects the water level to fall below a quarter of its starting height.
- Infiltration is treated as viable only above 1 x 10-6 metres per second, and a rate must not be assumed from the soil type.
- At least one metre of clearance to peak groundwater is needed. Groundwater monitoring is typically required between November and May.
- A back-up drainage option is acceptable only at outline stage. Full applications and discharge of conditions need site investigation, testing and monitoring.
The county is a statutory consultee on major development only. On smaller sites the district or borough council decides what it needs.
Rushmoor Borough Council (Aldershot and Farnborough)
Policy NE8 of the Rushmoor Local Plan requires sustainable drainage in all flood zones, on brownfield and greenfield sites. The plan notes that infiltration will be inappropriate in parts of the borough because of the geology. The borough’s flood risk assessment identifies very significant constraints along the Blackwater corridor, and areas around Aldershot and from Farnborough Green to North Camp as highly compatible.
Hart District Council (Fleet, Hook, Yateley)
Policy NBE5 of the Hart Local Plan requires sustainable drainage in major developments unless it is shown to be inappropriate. The validation requirements ask for a sustainable drainage strategy on all major development, and a flood impact form on smaller schemes.
Hart’s flood risk guidance says test results are needed to confirm that infiltration is possible, that infiltration is unlikely to be accepted on clay, and asks for a back-up option. Its 2016 flood risk assessment asks for an infiltration test in accordance with BRE365.
East Hampshire District Council (Alton, Bordon, Four Marks)
Policy CP25 of the Joint Core Strategy requires no net increase in surface water runoff and gives priority to sustainable drainage. It notes that chalk areas can be prone to groundwater flooding. The district’s flood risk assessment identifies constraints on infiltration drainage across most of the urban areas, which makes a measured result more important.
Part of the district is in the South Downs National Park, where the National Park Authority decides planning applications. Its local validation list asks for a surface water drainage strategy on all major development.
What this means for your test
- Ask your designer for the positions and depths first. A test in the wrong place or at the wrong depth may not support the design. Send us the specification and we quote for those locations.
- Allow for three fills. The ground sets the pace, and a slow fill can run overnight. We book three consecutive days. See how long a percolation test takes.
- The fall needs to be recorded, not projected. Hampshire does not accept an extrapolated result. Our Percologger records the water level between visits, including overnight where the site can be left safely, so the report shows how far the level actually fell.
- Groundwater monitoring is separate. Where the reviewer asks for winter groundwater monitoring, that is a different piece of work from the infiltration test. Ask your designer whether your site needs it.
- A poor result is still an answer. If the ground does not drain well enough, the report says so, and your designer moves to the next option. A test does not guarantee that a soakaway will be approved.
What a test costs
£1,500 fixed for one test location. That covers excavation of the trial pit, water, the three fills with Percologger monitoring, reinstatement and your report. There is no VAT to add. Further test locations are quoted separately.
The price does not change if the ground drains slowly. Your report follows the day after the final testing visit.
Questions about tests for planning
Should the soakaway test be done before I apply for planning, or after?
Earlier is safer. Surrey County Council says infiltration test results should accompany planning applications, and asks for a justification and a desk study of ground conditions when they are missing. Hampshire County Council accepts a back-up drainage option only at outline stage; full applications and discharge of conditions need site testing. If permission has already been granted with a drainage condition, the test results are part of what discharges it.
Will the council accept a soakaway on clay?
It depends on the measured rate, not the soil name. Hampshire County Council treats infiltration as viable only above 1 x 10-6 metres per second and says a rate must not be assumed from the soil type. Hart District Council says infiltration is unlikely to be accepted on clay. A test gives your designer the measured figure; if the rate is poor, the report says so and the design moves to the next option in the drainage hierarchy.
Does one extension or a single new house need a BRE365 test?
The county flood authorities are statutory consultees on major development only, so smaller schemes are decided by the borough or district council and by Building Control. Approved Document H says percolation tests should be carried out to determine the capacity of the soil for a soakaway. Waverley asks for a surface water drainage strategy for all scales of development where surface water is created or affected. Ask your designer or the case officer what your application needs before booking.
Can you test where and how my drainage designer has specified?
Yes. Send us the designer's specification with the pit positions and depths. Hampshire's guidance asks for testing as close as possible to the proposed soakaway and at a similar depth, with the test repeated three times, so the positions matter as much as the result.
Arrange a soakaway test for your application
We are a family-run Farnham business testing across Surrey and Hampshire. Send us your postcode and your designer’s test requirements for a fixed-price quotation.
Get a quotation for my testOr call 01252 917235. Architects, engineers and planning consultants: see how we work with professionals.